P5-9 citation builders, inc., builds office buildings and

P5-9 Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture of the down payment. Occasionally, homes remain unsold for as long as three months after construction. In these situations, sales price reductions are used to promote the sale.

 

During 2011, Citation began construction of an office building for Altamont Corporation. The total contract price is $20 million. Costs incurred, estimated costs to complete at year-end, billings, and cash collections for the life of the contract are as follows:

 

2011 2012 2013 Costs incurred during the year $4,000,000 $9,500,000 $4,500,000 Estimated costs to complete as of year-end 12,000,000 4,500,000 – Billing during the year 2,000,000 10,000,000 8,000,000 cash collections during the year 1,800,000 8,600,000 9,600,000

 

Also during 2011, Citation began a development consisting of 12 identical homes. Citation estimated that each home will sell for $600,000, but individual sales prices are negotiated with buyers. Deposits were received for eight of the homes, three of which were completed during 2011 and paid for in full for $600,000 each by the buyers. The completed homes cost $450,000 each to construct. The construction costs incurred during 2011 for the nine uncompleted homes totaled $2,700,000.

 

Required:

1. Briefly explain the difference between the percentage-of-completion and the completed contract methods of accounting for long-term construction contracts.

2. Answer the following questions assuming that Citation uses the completed contract method for its office building contracts:

 

a. What is the amount of gross profit or loss to be recognized for the Altamont contract during 2011 and 2012?

b. How much revenue related to this contract will Citation report in its 2011 and 2012 income statements?

c. What will Citation report in its December 31, 2011, balance sheet related to this contract (ignore cash)?

3. Answer requirements 2a–2c assuming that Citation uses the percentage-of-completion method for its office building contracts.

4. Assume that as of year end 2012 the estimated cost to complete the office building is $9,000,000 and that Citation uses the percentage-of-completion method.

a. What is the amount of gross profit or loss to be recognized for the Altamont contract during 2012?

b. How much revenue related to this contract will Citation report in the 2012 income statement?

c. What will Citation report in its 2012 balance sheet related to this contract (ignore cash)?

5. When should Citation recognize revenue for the sale of its single-family homes?

 

6. What will Citation report in its 2011 income statement and 2011 balance sheet related to the single-family home business (ignore cash in the balance sheet)?

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.